High Performance Builder Spotlight - This 1963 mid-century modern home in Las Vegas got an energy-efficiency overhaul, improving performance from a HERS score of 123 to -2. - January 2010

Building Media, Inc. and Green Builder® Media, LLC, have teamed with the U.S. Department of Energy and corporate sponsors on a net-zero energy remodel demonstration home for visitors at the 2010 International Builders Show in Las Vegas. Their ReVISION Vegas home is a deep retrofit of a 1963 ranch home that will cut energy bills by at least 60%, not counting photovoltaics.

A show piece in its time, the 1,800-square-foot home was built on the then-new Stardust Golf Course, in the mid-century modern style with an open, singlestory floor plan, low-pitched roofs, post and beam construction, vaulted ceilings, and entire walls of windows. What was missing was insulation. By 2008, the house had utility bills up to $500 a month.

rvho_hot-dry_and_mixed 

Builder: Building Media, Inc. and Green Builder® Media, LLC

Project: Fourth home in the VISION demonstration home series, first retrofit

Size: 1,800 sq. ft. single-story home

“The trend is for people to live in smaller houses, closer to the city, and closer to transportation. With those trends, retrofits make sense.”Craig Savage, Co-President of Building Media

Craig Savage of Building Media, Inc. and his partners found the house in foreclosure with $456,000 in notes against it. They bought it for $145,000, and Savage estimates the cost of the retrofit at about $150,000 including labor and purchased and donated materials.

Before any retrofit work began, Building America’s Consortium for Advanced Residential Buildings (CARB) team, led by Steven Winter Associates, conducted a thorough analysis of the home including air leakage testing of the ducts and whole house, Manual-J calculations and Energy Gauge U.S.A. analysis. CARB will conduct a year of energy use monitoring when the retrofit is complete.

The owners removed the old stucco and decayed wood siding and filled the 2x4, 16-inch on-center wall cavities with 3.5 inches of BASF ENERTITE® opencell spray-applied polyurethane foam insulation, covered by half-inch OSB, Tyvek® StuccoWrap®, and Dryvit Outsulation® RMD system, which includes 2 inches of rigid EPS. “It’s an absolute thermos bottle of a wall,” said Savage.

Most of the ceiling had been drywalled in a 1990 remodel following a fire. The old torch-down roofing and OSB roof sheathing were removed, and the rafter cavities were filled with 8 inches of BASF COMFORT FOAM®  closed-cell sprayapplied insulation and air barrier then covered with 5/8-inch OSB. Over this, PetersenDean Roofing and Solar Systems laid DuPont™  RoofLiner underlayment. Next, wood 1x3 spacers were nailed vertically at 2-foot intervals from eave to ridge and topped with another set of 1x3 spacers laid horizontally. The spacers provide a 1.5-inch gap under the MBCI BattenLok®  standing seam ENERGY STAR “cool” metal roof, which draws hot air up and out of the roof ridge vent.

All of the home’s single-pane, wood- or aluminum-framed windows were replaced with Milgard triple-pane, low-emissivity, argon-filled, fiberglass-framed windows. A new electric heat pump, tankless gas water heater, solar hot water heater, LED and CFL lights, and an upgraded pool pump add to the energy savings.

Bombard Renewable Energy donated 27 roof-mounted SunPower®  photovoltaic panels yielding 4.8 kW of AC electricity. When installed, CARB estimates the PV will bring the home’s HERS score from its pre-retrofit high of 123 to a -2, making this a net-zero energy home. Without the PV, the home achieves a very respectable HERS score of 44.

Building Media, Inc. has filmed each step of the retrofit for an online training program to be hosted on the Green Builder College website. Building Media, Inc., a wholly owned subsidiary of the DuPont Corp. that develops online training for the design/build community, teamed on this project with Green Builder®  Media, LLC, its partner on Green Builder College (www.greenbuildercollege.com).

Energy-Efficient Features

  • HERS Index Before: 123; HERS Index After: -2 with PV, 44 without

  • Walls Before: 2x4 16-inch on-center; stucco and board & batt siding, some R-11 fiberglass batt; After: Filled stud cavities with 3.5-inch BASF ENERTITE® open-cell spray-applied polyurethane foam insulation, covered by half-inch OSB, Tyvec® StuccoWrap®, Dryvit Outsulation® RMD system

  • Roof Insulation Before: none; Roof Insulation After: Filled rafter cavities with 8 inches of BASF COMFORT FOAM® closed-cell spray-applied insulation, 5/8-inch OSB, DuPont™ RoofLiner underlayment, and a 1.5-inch air gap under MBCI BattenLok® standing seam metal roof, reflective paint

  • Ducts Before: Unsealed R-6 flex duct in unconditioned space; 11.2% duct leakage; Ducts After: R-8 flex duct, mastic sealed. Compact duct design in conditioned space

  • HVAC Before: Two roof-mounted PTAC gas furnace/condenser units, 0.80 AFUE/SEER 10; HVAC After: Trane Weathertron® heat pump, 36,000-BTU/hr capacity 9 HSPF/SEER 18

  • Water Heating Before: 56% efficiency electric water heater; Water Heating After: Rinnai 0.87 EF tankless gas water heater, Solar hot water

  • Ventilation Before: N/A; Ventilation After: Constant 50 cfm exhaust ventilation with 6-watt Panasonic WhisperGreen ENERGY STAR fan

  • Windows Before: Single-pane, wood and aluminum-framed windows, U-1.11, SHGC-0.86; Windows After: Milgard triple-pane, low-e, fiberglass-framed, argon-filled windows; U-0.22, SHGC-0.19

  • Solar Before: N/A; Solar After: SunPower® 4.8 kW (AC) photovoltaic system

  • Lighting Before: 18 recessed can lights with incandescent bulbs; Lighting After: Cooper LED retrofit modules, Philips LED screw-based lamps, CFL bulbs

  • Pool Pump Before: old Pentair pool pump; Pool Pump After: Pentair high-efficiency pool pump

Building_America

U.S. Department of Energy Builders Challenge

DOE seeks to give every consumer the opportunity to buy a cost-neutral, net-zero energy home anywhere in the U.S. by 2030. Homes that qualify for this Builders Challenge must achieve a 70 or less on the EnergySmart Home Scale (E-Scale) which is based on the Home Energy Rating System (HERS) index (www.natresnet.org). The E-Scale allows homebuyers to understand—at a glance—how the energy performance of a particular home compares with others.

To learn more about the Builders Challenge and find tools to help market your homes, visit www.buildingamerica.gov/challenge.

EERE Information Center | 1-877-EERE-INF (1-877-337-3463) | www.eere.energy.gov/informationcenter

For information on Building America visit www.buildingamerica.gov. The website contains expanded case studies, technical reports, and best practices guides.

Certificate of Product Ratings - Trane XL20i Weathertron

   
Green Builder Ad